Monday, February 23, 2015

Report recommends spending $13.2 million plus for Joplin R-8 facilities

Be prepared for the tax levy increase proposal that is surely heading our way.

The final report of the Long Range Facilities Committee will be presented to the Joplin R-8 Board of Education when it meets at 6 p.m. Tuesday and it includes a recommended $13.2 million in expenditures over the next five years.

Superintendent C. J. Huff has been talking about the need for a levy increase to accomplish the things that needed to be done in the school district and during the August board meeting, the board took steps that would permit them to go for a levy increase this year if it decides on that route.

Committee members who asked what the district could pay for were told not to worry about that and just determine what is needed.

One thing that is not being recommended is new carpeting for the administration as it moves into the Memorial Middle School building. The Huff Administration will recommend spending $59,264 on that, an item which, as usual, can be found in the board's consent agenda.


These are the expenditures that the report recommends and what year the projects would be done:


Cecil Floyd
Lighting $75,000 2016-2017
Security enhancements $20,000 2016-2017
Paint $25,000 2017-2018
Playground equipment $100,000 2018-2019
Intercom $25,000 2018-2019
Hot water system- $20,000 2019-2020

Columbia
Playground rubber $60,000 2015-2016
Foundation repair $500,000 2015-2016
Carpeting $50,000 2016-2017
Rooftop HVAC- $150,000 2016-2017
Relocate Kitchen- $100,000 2017-2018
Paint $25,000 2018-2019
Lighting $100,000 2018-2019
Hot Water System $15,000 2018-2019
Restroom improvements $50,000 2019-2020
Intercom system $25,000 2019-2020

Eastmorland
Playground rubber $20,000 2015-2016
Intercom $25,000 2017-2018
Asphalt sealing $25,000 2017-2018
Paint $25,000 2018-2019
Lighting $100,000 2018-2019
Storage Building $5,000 2018-2019
Roof $150,000 2019-2020

Irving
Phase II Grounds Modification $100,000 2015-2016

Jefferson
Intercom $25,000 2016-2017
Roof $250,000 2016-2017
ADA Locks $50,000 2016-2017
Security Enhancements $20,000 2016-2017
Windows $100,000 2017-2018
Paint $25,000 2018-2019
Lighting $100,000 2019-2020

Kelsey Norman
Windows $100,000 2016-2017
Lighting $100,000 2017-2018
Intercom $25,000 2017-2018
ADA Locks $50,000 2017-2018
Paint $25,000 2018-2019
Roof $100,000 2019-2020

McKinley
Foundation issue $250,000 2015-2016
Lighting $100,000 2016-2017
Paint $50,000 2017-2018
Asphalt sealing $25,000 2017-2018
Rooftop HVAC $150,000 2018-2019
Demolish old gym, add parking $300,000 2019-2020

Royal Heights
Playground equipment with rubber $100,000 2015-2016
ADA locks $50,000 2015-2016
Lighting $100,000
Paint $25,000 2016-2017
Intercom- $25,000 2017-2018
Windows $150,000 2018-2019
Roof $250,000 2018-2019

Soaring Heights
Basketball and soccer goals $20,000 2015-2016

Stapleton
Rubber play area $20,000 2015-2016
Rooftop HVAC $150,000 2015-2016
Asphalt sealing $50,000 2017-2018
Paint $50,000 2018-2019
Lighting $100,000 2018-2019
Roof $150,000 2019-2020

West Central
Roof $200,000 2015-2016
Playground rubber $75,000 2015-2016
Asphalt walking track $100,000 2016-2017
Carpet $50,000 2016-2017
Intercom $25,000 2017-2018
Rooftop HVAC $150,000 2018-2019
Media Center Remodeling $50,000 2018-2019
ADA Locks $50,000 2018-2019
Restroom Remodeling $500,000 2018-2019
Lighting $100,000 2019-2020
Relocate Kitchen $100,000 2019-2020

Roi S. Wood (Beacon and Flex)
Rubber playground $100,000 2015-2016
Asphalt sealing $15,000 2019-2020

East Middle School
Nothing listed

North Middle School
Carpet $100,000 2017-2018
Paint $50,000 2019-2020
Lighting $150,000 2019-2020
Asphalt $75,000 2019-2020

South Middle School
Carpet $100,000 2016-2017
Paint -$50,000 2018-2019
Lighting $150,000 2018-2019
Asphalt sealing $75,000 2018-2019

Joplin High School
West parking lots $250,000 2015-2016
Industral Arts Dust Control $75,000 2015-2016
Additional Gym Lockers $100,000 2016-2017

Franklin Technology Center
Window tint $50,000 2015-2016
HVAC Shop Modifications $100,000 2015-2016

Buildings, Grounds, and Transportation
Fuel Systems Update $100,000 2015-2016
Restroom $50,000 2016-2017
Service Vehicles $500,000 ($100,000 for each of the next five years)
Buses $3,000,000 ($600,000 for each of the next five years)
Mowing Equipment $250,000 ($50,000 for each of the next five years)
Custodial Equipment $75,000 ($15,000 for each of the next five years)

Food Service Warehouse
Safe room $10,000 2015-2016
Asphalt $20,000 2016-2017

Junge Field
Turf replacement $500,000 2017-2018
Track resurfacing $100,000 2017-2018
Asphalt $25,000 2019-2020

Emerson Elementary Building
Demolition $700,000

Memorial Education Building (Administration)
Asphalt sealing $50,000 2019-2020
Roof $250,000 2016-2017
Lighting $200,000 2019-2020
Hot Water System $20,000 2019-2020

4 comments:

  1. Anonymous7:31 PM

    Is this after the additional 14 million dollar loan that only one out of 15 banks approved them for less than a month ago?! RIDICULOUS!

    ReplyDelete
  2. Anonymous7:45 PM

    What is not listed is the $600,000 per year for the overages at the high school. It is coming out of the capital budget for the next five years. What about the remaining current budget of $900,000 that is already budgeted. Shouldn't these items come from the budget??

    ReplyDelete
  3. Anonymous9:10 PM

    Randy-please note as a followup to the St. Joseph school audit

    St. Joseph dumps its superintendent after a scathing audit. The school board voted 6-0 to start termination procedures on Friday.

    http://www.ksl.com/?nid=157&sid=33574299&s_cid=rss-157

    ReplyDelete
  4. Anonymous7:18 AM

    To me this basically tells me that they will not be tearing down and building new West Central or Columbia schools. Instead just patching up the old buildings. Also some of these schools were just repainted after the tornado, why do they need painted again?

    ReplyDelete