(From MoDOT)Progress Update for Route 66 Improvement Project for Week of July 13
A project to make pavement, sidewalk, traffic and safety improvements along Missouri Route 66 (7th Street) in Joplin is underway. Here is an update of the work scheduled for the week of July 13.
Work scheduled:
-Contractor installing new sidewalk, curb and entrances between Florida Avenue and Ozark Avenue
Preparing for new roadway pavement between Ozark Avenue and the Canadian Pacific Kansas City (CPKC) Railroad tracks
Preparing for new roadway pavement between Ozark Avenue and the Canadian Pacific Kansas City (CPKC) Railroad tracks
-Placing hardware and pole bases for new signals at intersection with St. Louis Avenue
-Continue relocating sanitary sewer on south side of Route 66 (7thStreet)
-Liberty Electric continuing layout for new utility poles at intersection with St. Louis Avenue and supporting existing poles between St. Louis Avenue and Ozark Avenue as needed
-Missouri American Water relocating service tie-ins to new water line between Florida Avenue and McConnel Avenue
-Additional Missouri American Water crews working between Patterson Avenue and Florida Avenue and working on additional water line crossings as needed
-Spire continuing utility relocation work at intersection with Main Street
-AT&T coordinating with other utilities and the contractor for relocation of the pole at the southeast corner of intersection with St. Louis Avenue and planning for additional relocations between Pearl Avenue and Wall Avenue
-Bluebird Fiber continuing to bore new conduit between St. Louis Avenue and Murphy Boulevard on north side of Route 66 (7thStreet)
-Lumen Fiber continuing utility relocation work at Florida Avenue
-Allo Fiber coordinating with other utilities on additional crossings of Route 66 (7th Street) west of Main Street
-Sparklight Internet coordinating transfers onto new Liberty poles as they are installed
Traffic Impacts
At least one lane of Route 66 (7th Street) OPEN in both directions
Access to all business will be maintained at all times
Signs and message boards will alert drivers approaching the work zone
No signed detours
Drivers should find alternate routes around the work zone
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or scheduling conflicts could alter the work schedule.
Project Details
The project will make improvements along the Route 66 (7th Street) corridor in Joplin between Jasper County Route P (Schifferdecker Avenue) and Loop 49 (Range Line Road).
As part of this project, the contractor will rebuild the pavement, bring sidewalks up to Americans with Disabilities Act (ADA) standards, and upgrade and replace several traffic signals along the corridor.
This contract also includes a project to rehabilitate the Oak Street bridge over I-49 in Carthage. That project is likely to start in 2027.
Project Information:Prime Contractor: D&E Plumbing & Heating LLC, Nixa
Construction Cost: $61.6 million
Contract Completion Date: December 1, 2028