Progress Update for Route 66 Improvement Project for Week of Sept. 7
A project to make pavement, sidewalk, traffic and safety improvements along Missouri Route 66 (7th Street) in Joplin is underway. Here is an update of the work scheduled for the week of September 7.
Drivers are reminded that access to all businesses along Route 66 (7thStreet) will be maintained during hours of operation.
Work scheduled
Contractor installing new storm sewer on the north side of Route 66 (7th Street) between St. Louis Avenue and Park Avenue
Contractor is planning for additional storm sewer work on the north side of Route 66 (7th Street) between Highland Avenue and Florida Avenue
CLOSING Ozark Avenue south of Route 66 (7th Street) beginning Tuesday, September 8 for replacement of pavement
Florida Avenue currently CLOSED on both sides of Route 66 (7thStreet) for pavement replacement, installation of new traffic signal infrastructure and to accommodate temporary traffic shift
Pavement replacement for south half of Route 66 (7th Street) between McConnel Avenue and just east of Florida Avenue planned for September 13 & 14 (work done outside of regular business hours)
City of Joplin working to replace sidewalk on south side of Route 66 (7th Street) just east of Ozark Avenue
Liberty Electric crews planning for installation of new light poles within the next couple of weeks, but no current work on Route 66 (7th Street)
Missouri American Water crews relocating water line on the north side of Route 66 (7th Street) between School Avenue and Michigan Avenue
Missouri American Water crews relocating and doing tie-in work on water line on north side of Route 66 (7th Street) between Pennsylvania Avenue and Kentucky Avenue
Missouri American Water crews relocating and doing tie-in work on both sides of Route 66 (7th Street) between Kentucky Avenue and Grand Avenue
Missouri American Water plans road closures along Route 66 (7thStreet) at Vermont Avenue, New Hampshire Avenue and High Avenue
AT&T crews working during nighttime hours relocating utilities between Minnesota Avenue and St. Louis Avenue.
AT&T crews planning for excavation at the alley between Pearl Avenue and Wall Avenue
Lumen Fiber crews relocating utilities at Florida Avenue north of Route 66 (7th Street)
Traffic Impacts
At least one lane of Route 66 (7th Street) OPEN in both directions
Access to all business will be maintained during hours of operation
Signs and message boards will alert drivers approaching the work zone
No signed detours
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Project Details
The project will make improvements along the Route 66 (7th Street) corridor in Joplin between Jasper County Route P (Schifferdecker Avenue) and Loop 49 (Range Line Road).
As part of this project, the contractor will rebuild the pavement, bring sidewalks up to Americans with Disabilities Act (ADA) standards, and upgrade and replace several traffic signals along the corridor.
This contract also includes a project to rehabilitate the Oak Street bridge over I-49 in Carthage. That project is likely to start in 2027.
Project Information
Prime Contractor: D&E Plumbing & Heating LLC, Nixa
Construction Cost: $61.6 million
Contract Completion Date: December 1, 2028