(From MoDOT)Progress Update for Route 66 Improvement Project for Week of July 27
A project to make pavement, sidewalk, traffic and safety improvements along Missouri Route 66 (7th Street) in Joplin is underway. Here is an update of the work scheduled for the week of July 27.
Work scheduled
Contractor installing new sidewalk, curb and entrances between Florida Avenue and Ozark Avenue
Excavation and placing new stormwater structures between Florida Avenue and Ozark Avenue
Preparing for new roadway pavement between Ozark Avenue and the Canadian Pacific Kansas City (CPKC) Railroad tracks
City of Joplin crews maintaining steel plates at intersection with St. Louis Avenue ahead of completion of sanitary sewer work
City of Joplin preparing for sanitary sewer work at Ozark Avenue
Liberty Electric preparing for remainder of utility relocation work at St. Louis Avenue
Missouri American Water working on water line between Florida Avenue and St. Louis Avenue
AT&T coordinating relocation of pole at the southeast corner of intersection at St. Louis Avenue
AT&T coordinating transfer of overhead lines to new poles
Bluebird Fiber boring new conduit
Lumen Fiber relocating fiber at Florida Avenue
Sparklight Internet coordinating transfers onto new Liberty poles as they are installed
Traffic Impacts
At least one lane of Route 66 (7th Street) OPEN in both directions
Access to all business will be maintained at all times
Signs and message boards will alert drivers approaching the work zone
No signed detours
Drivers should find alternate routes around the work zone
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or scheduling conflicts could alter the work schedule.
Project Details
The project will make improvements along the Route 66 (7th Street) corridor in Joplin between Jasper County Route P (Schifferdecker Avenue) and Loop 49 (Range Line Road).
As part of this project, the contractor will rebuild the pavement, bring sidewalks up to Americans with Disabilities Act (ADA) standards, and upgrade and replace several traffic signals along the corridor.
This contract also includes a project to rehabilitate the Oak Street bridge over I-49 in Carthage. That project is likely to start in 2027.
Project Information
Prime Contractor: D&E Plumbing & Heating LLC, Nixa
Construction Cost: $61.6 million
Contract Completion Date: December 1, 2028
Construction Cost: $61.6 million
Contract Completion Date: December 1, 2028