Intervention deadline set for Liberty Utilities request to build gas electric generating facility in Joplin
(From Missouri Public Service Commission)
The Missouri Public Service Commission (PSC) has set an intervention deadline of November 12, 2025, for a Certificate of Convenience and Necessity (CCN) application from The Empire District Electric Company d/b/a Liberty to build a gas electric generating facility in Joplin, Missouri.
On October 24, 2025, Liberty filed an application for a CCN to construct a 250-megawatt combustion turbine generator at its State Line Power Station.
Applications to intervene and participate in this case must be filed with the Secretary of the Missouri Public Service Commission, P.O. Box 360, Jefferson City, Mo. 65102-0360, or by using the Commission’s Electronic Filing and Information System (EFIS) at psc.mo.gov.
Individual citizens wishing to comment may click the link(s) below, or contact either the Office of the Public Counsel (Governor Office Building, 200 Madison Street, Suite 650, P.O. Box 2230, Jefferson City, Mo. 65102-2230, telephone 866-922-2959, email mopco@opc.mo.gov) or the Public Service Commission Staff (P.O. Box 360, Jefferson City, Mo. 65102, telephone 800-392-4211, email pscinfo@psc.mo.gov). The Office of the Public Counsel is a separate state agency that represents the general public in matters before the Commission.
Subscribe to:
Post Comments (Atom)

5 comments:
It sounds like turbines and solar must have just been an overpriced pipe dream. I bet this will cost lest that half and actually work.
Lest?
Only if it lowers liberty’s prices to consumers.
If you think prices are going down you haven
Yes it’s obviously a typo, I apologize, one of these days when you make a mistake don’t forget to apologize
Post a Comment