When it meets 6 p.m. Monday, the Joplin City Council is expected to approve a contact with Jeff Asbell Escavating for demolition and grading of the site for the new Joplin Public Library.
The company submitted the low bid of $319,095.50.
The council will have 30 days to issue the order for the company to begin its work. After that, the contract specifies that the work be concluded in 60 days.